Contract No: HK/2009/05 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work (Stage
1) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A and FEp-06/364/2009/a Monthly Environmental Monitoring
& Audit Report
- january 2011 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
4 February 2011 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring
6.4 Review
of the Reasons for and the Implications of Non-compliance
6.5 Summary
of action taken in the event of and follow-up on non-compliance
7. Cumulative Construction Impact due to the
Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2
Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/17
Table 3.3 Summary
of submission status under FEP-03/364/2009 Condition
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. 04/HY/2006
Table 3.5 Summary
of submission status under FEP-04/364/2009/A Condition
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.7 Summary
of submission status under FEP-02/364/2009 Condition
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.9 Summary
of submission status under FEP-01/364/2009 Condition
Table
3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Table
3.11 Summary
of submission status under FEP-05/364/2009/A Condition
Table
3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table
3.13 Summary
of submission status under FEP-06/364/2009/A Condition
Table 4.1 Noise
Monitoring Station
Table 4.2 Real
Time Noise Monitoring Station
Table 4.3 Air
Monitoring Station
Table 5.1 Noise
Monitoring Stations for Contract no.
HY/2009/17
Table 5.2 Noise
Monitoring Stations for Contract no.
04/HY/2006 and HY/2009/18
Table 5.3 Noise
Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Table 5.4 Noise
Monitoring Station for Contract nos. HY/2009/15
Table 5.5 Real
Time Noise Monitoring Station for Contract no. HY/2009/17
Table 5.6 Air
Monitoring Stations for Contract no. HY/2009/17
Table 5.7 Air
Monitoring Stations for Contract no. 04/HY/2006 and HY/2009/18
Table 5.8 Air
Monitoring Stations for Contract no. HK/2009/01
Table 5.9 Air
Monitoring Station for Contract no. HK/2009/02
Table
5.10 Air Monitoring Station for Contract no. HY/2009/15
Table
5.11 Details
of Waste Disposal for Contract no. HY/2009/17
Table
5.12 Details
of Waste Disposal for Contract no. 04/HY/2006
Table
5.13 Details
of Waste Disposal for Contract no. HK/2009/01
Table
5.14 Details
of Waste Disposal for Contract no. HK/2009/02
Table
5.15 Details
of Waste Disposal for Contract no. HY/2009/18
Table
5.16 Details
of Waste Disposal for Contract no. HY/2009/15
Table 8.1 Summary
of Environmental Inspections for Contract no. HY/2009/17
Table 8.2 Summary
of Environmental Inspections for Contract no. 04/HY/2006
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project
Organization Chart
Figure 4.1
Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration
Certificates
Appendix
5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and Graphical Presentations
Appendix
5.3 Air Quality Monitoring
Results and Graphical Presentations
Appendix 5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of
Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot
- Advanced piling works under FEP-03/364/2009
·
Piling
Works.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
·
No major
construction activity was undertaken in reporting month. Only preparation works
was commenced in the reporting month.
·
Condition
survey / Instrumentation Manholes Survey
·
Cable
detection and excavation of trial pit
·
Hoarding
erection
·
Erection
of CLC
·
Tree
transplanting
·
Trial
installation of coupler in CR3
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
·
Modification
of bus bays at the bus terminus
·
Modification
of traffic island at
·
Resurfacing
Works at
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
·
No major
construction activity was undertaken in reporting month.
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
No major
construction activity was undertaken in reporting month.
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
No major
construction activity was undertaken in reporting month.
Noise Monitoring
Air Monitoring
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/17 -
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works
under FEP-03/364/2009
·
Piling
Works
Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
No major
construction activity was undertaken in next reporting month. Only preparation
works was commenced.
·
Condition
survey / Instrumentation Manholes Survey
·
Cable
detection and excavation of trial pit
·
Hoarding
and project signboard erection
·
Erection
of CLC
·
Tree
transplanting
·
Provision
of site welfare facilities
·
Trial
installation of coupler in CR3
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
·
Resurfacing
Works at
· Construction of Planting Area at
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
·
No major construction activities are anticipated in coming reporting month.
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
No major construction activities are anticipated in coming reporting month.
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
No major construction activity was
undertaken in reporting month.
1.1.1.
Lam Geotechnics
Limited (LGL) has been appointed to work as the Environmental Team (ET) under
Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A and FEP-06/364/2009/A to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report
presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A
Manual and “Environmental Monitoring and Audit Requirements” under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009,
FEP-04/364/2009/A, FEP-05/364/2009/A and FEP-06/364/2009/A during the period
28th December to 27th
January 2011. The cut-off date of reporting is at 27th of each reporting
month.
Section
1 Introduction
– details the scope and structure of the report.
Section
2 Project Background
– summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section
3 Status of Regulatory
Compliance – summarizes the status of valid
Environmental Permits / Licenses during the reporting period.
Section
4 Monitoring Requirements
– summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section
5 Monitoring Results
– summarizes the monitoring results obtained in the reporting period.
Section
6 Compliance Audit
– summarizes the auditing
of monitoring results, all exceedances environmental parameters.
Section
7 Cumulative Construction
Impact due to the Concurrent Projects –
summarizes the relevant
cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section
8 Site Inspection –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of
summons and Prosecution – summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
“Wan Chai
Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass
and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose
of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North
and North Point for construction of the Central-Wan Chai Bypass and Island
Eastern Corridor Link (CWB). Land formed under the project will be developed as
a world-class waterfront promenade joining that at the new Central waterfront
for public enjoyment.
2.1.3.
There is a
compelling and present need for the CWB to provide relief to the very congested
2.2.1.
Design and Construction of Central – Wan Chai Bypass and Island Eastern
Corridor Link under the Project involves the construction and operation of a
trunk road and its road tunnel more than 800m in length between portals that is
shown at Figure 2.1.
2.2.2.
The study area encompasses existing
developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
·
Tunnel
control buildings and ventilation buildings;
·
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
·
Associated
road lighting, road signing, traffic control and surveillance system; and
·
Other
associated works.
2.2.3.
The project also
contains various Schedule 2 DPs that, under the EIAO, require Environmental
Permits (EPs) to be granted by the DEP before they may be either constructed or
operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads |
Schedule
2, Part I, A.1 and A.7 |
Trunk
road and road tunnel more than 800 m in length |
DP2 |
Road P2
and other roads which are classified as primary/district distributor roads |
Schedule
2, Part I, A.1 |
Primary
/ district distributor roads |
DP3 |
Reclamation
works including associated dredging works |
Schedule
2, Part I, C.1 and C.12 |
Reclamation
more than 5 ha in size and a dredging operation less than 100 m from a
seawater intake point |
DP5 |
Wan Chai
East Sewage Outfall |
Schedule
2, Part I, F.5 and F.6 |
Submarine
sewage pipelines with a total diameter more than 1,200 mm and include a
submarine sewage outfall |
DP6 |
Dredging
for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui |
Schedule
2, Part I, C.12 |
A
dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the
multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided
accordingly to facilitate the implementation of EM&A programme and to
streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2.
In the reporting
month, advance piling work at FEHD Whitfield Depot
under Contract no. HY/2009/17 was commenced on 5 October 2010 and completed on
20 January 2011. The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central
- Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
Anticipated to be commenced in January 2011 |
04/HY/2006 |
Reconstruction
of Bus Terminus near |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai
Development Phase II - Central - Wan Chai Bypass at |
DP1, DP2 |
Pending |
HK/2009/02 |
Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)
(CWB Tunnel) |
DP1 |
Pending |
HY/2009/15 |
Central-Wanchai
Bypass – Tunnel ( |
DP1 |
Pending |
2.4.1.
Civil Engineering and Development Department and Highways Department are
the overall project controllers for the Wan Chai Development Phase II and
Central-Wan Chai Bypass respectively. For the construction phase of the
Project, Project Engineer, Contractor(s), Environmental Team and Independent
Environmental Checker are appointed to manage and control environmental issues.
2.4.2.
The proposed
project organization and lines of communication with respect to environmental
protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer
for WDII |
Principal
Resident Engineer |
Mr.
Frankie Fan |
2587
1778 |
2587 1877 |
Engineer
for CWB |
Principal
Resident Engineer |
Mr. Peter
Poon |
3916
1818 |
3529 2829 |
|
Lam Woo &
CO., LTD. |
Contractor
under Contract no. HY/2009/17 |
Project
Manager |
Mr. K.
S. Law |
9090
1378 |
2566 7522 |
Construction
Manager / Sub Agent |
Mr. Joe
Tsang |
9725-5874 |
|||
Site Agent |
Mr.
Daniel Chan |
9372
0495 |
|||
Environmental
Officer |
Mr. Andy
Mak |
6461
3065 |
|||
Chiu
Hing Construction & Transportation Co. Ltd. |
Contractor
under Contract no. 04/HY/2006 |
Contract Manager |
Mr. Frederick Tsui |
2967 6363 |
2967 6366 |
Senior Site Agent |
Mr. Alvin Ma |
2967 6363 |
2967 6366 |
||
Environmental Consultant |
Mr. Jimmy Cheng |
2965 0898 |
2556 9172 |
||
Chun Wo –
Leader Joint Venture |
Contractor
under Contract no. HK/2009/01 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Mr. Ho Wing Tai |
9306 1356 |
|||
Construction Manager |
Mr. David Wong |
9653 8635 |
|||
Construction Manager |
Mr. Wilson Lau |
5183 1270 |
|||
Construction Manager |
Mr. Alex Tsang |
9194 9383 |
|||
Environmental Officer (Compliance
Manager) |
Mr.Ho Wing Tai |
9306 1356 |
|||
Environmental
Engineer |
Mr. Ken
Yang |
9262
6791 |
|||
Chun Wo –
CRGL Joint Venture |
Contractor
under Contract no. HK/2009/02 |
Project
Manager |
Mr. Chan
Sing Cho |
3658
3002 |
2827 9996 |
Site
Agent |
Mr. Eric
Lam |
3658-3048 |
|||
Deputy Site
Agent |
Mr.
Anthony Wu |
3658-3004 |
|||
Environmental
Officer (Compliance Manager) |
Mr.
Barry Leung |
3658
3031 |
|||
Environmental
Engineer |
Ms.
Flora Ng |
3658-3064 |
|||
Leighton
Contractors ( |
Contractor
under Contract no. HY/2009/18 |
Site
Agent |
Mr. Brian
Gillon |
2214 7700 |
2140 6799 |
Deputy
Site Agent |
Mr. Desmond
Sze |
2214 7703 |
|||
Quality
& Env. Manager |
Mr. Stephen
Moc |
2214 7720 |
|||
Environmental
Officer |
Mr. Anfernee
Chow |
2214 7721 |
|||
Environmental
Supervisor |
Mr. Dennis
Yu |
2214 7738 |
|||
|
Contractor
under Contract no. HY/2009/15 |
Project
Manager |
Mr. M Y
Wong |
2823
7879 |
2566 2192 |
Site
Agent |
Mr. Leung
Kwok Yiu |
9026
8808 |
|||
Head of
construction |
Mr. Simon
Tang |
9022
6060 |
|||
Construction
Manager |
Mr. C K
Kwok |
9779
2162 |
|||
Assistant
Construction Manager (East) |
Mr. Gene
Cheung |
6105
4880 |
|||
Assistant
Construction Manager (West) |
Mr. Tony
Chiu |
9090
0606 |
|||
Section
Agent (East) |
Mr. Jason
Chan |
9254
1635 |
|||
Section
Agent (West) |
Mr. Tang
Ka Tung |
9473
4771 |
|||
Environmental
Manager |
Ms. Anna
Yu |
9473
1945 |
|||
Environmental
Officer |
Mr
Kelven Yip |
9669
5447 |
|||
ENVIRON
Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr.
David Yeung |
3743
0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In the reporting month, the principal work activities of individual
contracts are included as follows:
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street
under FEP-04/364/2009/A
· Modification of bus bays at the bus terminus
· Modification of traffic island at
·
Resurfacing
Works at
Contract no. HY/2009/17 -
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works
under FEP-03/364/2009
·
Piling
Works
Contract no. HY/2009/18 - Central
- Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
·
No major
construction activity was undertaken in reporting month. Only preparation works
was commenced in the reporting month.
·
Condition
survey / Instrumentation Manholes Survey
·
Cable
detection and excavation of trial pit
·
Hoarding
erection
·
Erection
of CLC
·
Tree
transplanting
·
Trial
installation of coupler in CR3
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
·
No major
construction activity was undertaken in reporting month.
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
·
No major
construction activity was undertaken in reporting month.
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (
·
No major
construction activity was undertaken in reporting month.
2.4.4.
In coming
reporting month, the principal work activities of individual contracts are
anticipated as follows:
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
·
Resurfacing Works at
· Construction of Planting Area at
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Piling Works.
Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
No major
construction activity was undertaken in next reporting month. Only preparation
works was commenced.
·
Condition
survey / Instrumentation Manholes Survey
·
Cable
detection and excavation of trial pit
·
Hoarding
and project signboard erection
·
Erection
of CLC
·
Tree
transplanting
·
Provision
of site welfare facilities
·
Trial
installation of coupler in CR3
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
·
No major construction activity is
anticipated in coming reporting month.
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
No major construction activity is
anticipated in coming reporting month.
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
No major construction activity
was undertaken in reporting month.
3.1.1.
A summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project is shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Valid |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
3.1.2.
Due to the
multi-contract nature of the Project, the status of permits and/or licences
under the individual contract(s) are presented as below:
Contract no. HY/2009/17 - Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under
FEP-03/364/2009
3.1.3.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-03/364/2009 for contract no. HY/2009/17 are shown in Table 3.2 and Table 3.3.
Table
3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 – 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 May 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3 Summary
of submission status under FEP-03/364/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 September 2010 |
Conditions 2.7 and 2.8 |
Submission of works
schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management Plan |
1 September 2010 |
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus
near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.4.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-04/364/2009/A for contract no. 04/HY/2006 are shown in Table
3.4 and Table 3.5.
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. 04/HY/2006
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
N/A |
Valid |
Notification of Works Under APCO |
322225 |
7 Oct 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7005123 |
9 Mar 2007 |
N/A |
Valid |
Table 3.5 Summary
of submission status under FEP-04/364/2009/A
Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
11 June 2010 |
Conditions 2.7 and 2.8 |
Submission of works schedule and location plan |
11 June 2010 and 5 August 2010 |
Condition 2.9 |
Noise Management Plan |
19 October 2010 |
Condition 2.10 |
Landscape Plan |
26 Nov 10 |
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
3.1.5.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.6 and Table 3.7
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
Billing Account under Waste
Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan
2010 |
N/A |
Valid |
Table 3.7 Summary
of submission status under FEP-02/364/2009 Condition
EP Condition |
Submission |
Date of
Submission |
NIL |
NIL |
NIL |
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
3.1.6.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.8 and Table 3.9.
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July
2010 |
31 Jul
2015 |
Valid |
|
Billing Account under Waste Disposal
Ordinance |
7010255 |
10 Feb
2010 |
N/A |
Valid |
Registration as Chemical Waste Producer |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table 3.9 Summary
of submission status under FEP-01/364/2009 Condition
EP Condition |
Submission |
Date of
Submission |
NIL |
NIL |
NIL |
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
3.1.7.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-05/364/2009A for contract no.
HY/2009/18 are shown in
Table 3.10 and Table 3.11.
Table 3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
N/A |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
N/A |
Valid |
Discharge Licence |
WT00008229-2011 |
13 Jan 2011 |
31 Jan 2016 |
Valid |
Billing Account under Waste Disposal
Ordinance |
7011587 |
11-Oct-10 |
N/A |
Valid |
Registration as a Waste Producer |
WPN: 8335-121-L1048-04 |
17 Dec
2010 |
N/A |
Valid |
Table 3.11 Summary
of submission status under FEP-05/364/2009/A Condition
EP Condition |
Submission |
Date of
Submission |
NIL |
NIL |
NIL |
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
3.1.8.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.12 and Table 3.13
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
22 Nov 2010 |
N/A |
Valid |
|
22 Nov 2010 |
N/A |
Valid |
||
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Table 3.13 Summary of submission status under FEP-06/364/2009/A Condition
EP Condition |
Submission |
Date of
Submission |
NIL |
NIL |
NIL |
3.1.9.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix
3.1.
Noise Monitoring Stations
4.1.1.
The noise monitoring
stations for the Project are listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.
Table
4.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
M7e |
International Finance Centre
(Eastern End of Podium) |
M7w |
International Finance Centre
(Western End of Podium) |
Real time Noise Monitoring Stations
4.1.2.
The noise
monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the
monitoring works.
Table 4.2 Real Time
Noise
Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.3.
The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing,
statistical results such as L10 and L90 shall also be
obtained for reference.
4.1.4.
Noise monitoring
shall be carried out at all the designated monitoring stations. The monitoring
frequency shall depend on the scale of the construction activities. The
following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One set of measurements between
0700 and 1900 hours on normal weekdays.
4.1.5.
Real time noise
shall be carried out at the designated monitoring stations. The following is an
initial guide on the regular monitoring frequency for each station on a 24
hours daily basis when noise generating activities are underway:
·
One set of measurements between
0700 and 1900 hours on normal weekdays.
·
One set of measurements between 1900
and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.
·
One set of measurements between 2300
and 0700 hours on next day on everyday.
4.1.6.
If construction
works are extended to include works during the hours of 1900 – 0700 as well as
public holidays and Sundays, additional weekly impact monitoring shall be
carried out during respective restricted hours periods. Applicable permits
under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.7.
As referred to
in the Technical Memorandum ™ issued under the NCO, sound level meters in
compliance with the International Electrotechnical Commission Publications 651:
1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying
out the noise monitoring. Immediately prior to and following each noise
measurement the accuracy of the sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.8.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
4.1.9.
The sound level
meter shall be checked using an acoustic calibrator generating a known sound
pressure level at a known frequency before deployment to the site and during
each site visit. Measurements may be accepted as valid only if the calibration
level from before and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
4.2.1.
The air
monitoring stations for the Project are listed and shown in Table
4.3 and Figure 4.1.. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air
Monitoring Station
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
Future CWB site office at Wanchai Waterfront Promenade |
|
CMA4a |
Society for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to |
Wan Chai |
MA1e |
International Finance Centre
(Eastern End of Podium) |
Central |
MA1w |
International Finance Centre
(western End of Podium) |
Central |
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour and
24-hour TSP levels should be measured to indicate the impacts of construction
dust on air quality. The 24-hour TSP levels shall be measured by following the
standard high volume sampling method as set out in the Title 40 of the Code of
Federal Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant
data including temperature, pressure, weather conditions, elapsed-time meter
reading for the start and stop of the sampler, identification and weight of the
filter paper, and any other local atmospheric factors affecting or affected by
site conditions, etc., shall be recorded down in detail.
4.2.4.
For regular
impact monitoring, the sampling frequency of at least once in every six-days,
shall be strictly observed at all the monitoring stations for 24-hour TSP
monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three
times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume
samplers (HVSs) in compliance with the following specifications shall be used
for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6 - 1.7 m3 per minute
adjustable flow range;
·
Equipped with a timing / control
device with +/- 5 minutes accuracy for 24 hours operation;
·
Installed with elapsed-time meter
with +/- 2 minutes accuracy for 24 hours operation;
·
Capable of providing a minimum
exposed area of 406 cm2;
·
Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
·
Equipped with a shelter to
protect the filter and sampler;
·
Incorporated with an electronic
mass flow rate controller or other equivalent devices;
·
Equipped with a flow recorder for
continuous monitoring;
·
Provided with a peaked roof
inlet;
·
Incorporated with a manometer;
·
Able to hold and seal the filter
paper to the sampler housing at horizontal position;
·
Easily changeable filter; and
·
Capable of operating continuously
for a 24-hour period.
4.2.6.
Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7.
A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
4.2.8.
Filter paper of
size 8" x 10" shall be labeled before sampling. It shall be a clean
filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
4.2.9.
After sampling,
the filter paper loaded with dust shall be kept in a clean and tightly sealed
plastic bag. The filter paper shall then be returned to the laboratory for
reconditioning in the humidity controlled chamber followed by accurate weighing
by an electronic balance with readout down to 0.1 mg. The balance shall be
regularly calibrated against a traceable standard.
4.2.10. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.2.11. Current calibration certificates of equipments are
presented in Appendix
4.2.
5.0.1.
The
environmental monitoring will be implemented based on the division of works
areas of each designed project managed under different contracts with separate
FEP applied by individual contractors.
Overall layout showing work areas of various contracts, latest status of
work commencement and monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
In the reporting
month, the concurrent contracts are as follows:
Contract no.
04/HY/2006 –Reconstruction of Bus Terminus near
Contract no.
HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works under FEP-03/364/2009
5.0.3.
The environment
monitoring schedules for reporting month and coming month are presented in Appendix
5.1.
Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.1.1.
The proposed
division of noise monitoring stations for Contract no. HY/2009/17 are
summarized in Table 5.1 below:
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria
Centre |
5.1.2.
No action and
limit exceedance was recorded during day time and restricted hour period in the
reporting month. Noise monitoring results measured in this reporting period are
reviewed and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2.
Contract no. 04/HY/2006 – Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange
under FEP-05/364/2009/A
5.1.3.
The proposed
division of noise monitoring stations for Contract no. 04/HY/2006 and Contract
no. HY/2009/18 are summarized in Table 5.2 below:
Table 5.2
Noise Monitoring Stations for Contract no. 04/HY/2006 and HY/2009/18
Station |
Description |
M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
5.1.4.
No exceedance
was recorded in the reporting month. Noise monitoring results measured in this
reporting period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix
5.2.
5.1.5.
The commencement
of major construction works for Contract no. HY/2009/18 under FEP-05/364/2009A
is pending. Only preparation works was
commenced in the reporting month.
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009 and Contract no. HK/2009/02 - Wan Chai Development Phase II -
Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.6.
The commencement
of construction works for Contract no. HK/2009/01 and HK/2009/02 under
FEP-02/364/2009 and FEP-01/364/2009 respectively are pending. The proposed
division of noise monitoring stations are summarized in Table 5.3 below.
Table 5.3
Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour
Road Sports Centre |
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (
5.1.7.
The commencement of construction
works for Contract no. HY/2009/15 under FEP-06/364/2009/A is pending. The
proposed division of noise monitoring stations are summarized in
Table 5.3 below.
Table
5.4 Noise
Monitoring Station for Contract
nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun
Area |
M3a |
Tung Lo
Wan Fire Station |
Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.2.1.
The proposed
division of noise monitoring stations are summarized in Table 5.5
below. Real time noise monitoring for the piling works under contract no.
HY/2009/17 was commenced on 5 October 2010
Table 5.5 Real Time Noise
Monitoring Station for Contract no. HY/2009/17
District |
Description |
Tin Hau |
FEHD Hong Kong Transport Section
Whitefield Depot |
5.2.2.
No exceedance
was recorded in the reporting month. Real time noise monitoring results
measured in this reporting period are reviewed and summarized. Details of real
time noise monitoring results and graphical presentation can be referred to Appendix 5.4 .
Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under
FEP-03/364/2009
5.3.1.
The proposed
division of air monitoring stations are summarized in Table 5.6 below. Air
monitoring for the piling works under contract no. HY/2009/17 was commenced on
8 October 2010.
Table 5.6
Air
Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
CMA2a |
|
5.3.2.
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. 04/HY/2006 – Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange
under FEP-05/364/2009/A
5.3.3.
The proposed
division of air monitoring stations are summarized in Table 5.7 below.
Table 5.7
Air
Monitoring Stations for Contract no. 04/HY/2006 and HY/2009/18
Station |
Description |
MA1e |
International
Finance Centre (Eastern End of Podium) |
MA1w |
International
Finance Centre (Western End of Podium) |
5.3.4.
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
5.3.5.
The commencement
of major construction works for Contract no. HY/2009/18 under FEP-05/364/2009A
is pending. Only preparation works was
commenced in the reporting month.
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
5.3.6.
Air quality monitoring will be commenced depending on
the commencement of work for Contract no. HK/2009/01 under FEP-02/364/2009. The proposed
division of air monitoring stations are summarized in Table 5.8 below.
Table 5.8
Air
Monitoring Stations
for Contract
no. HK/2009/01
Station |
Description |
CMA5a |
Children
Playgrounds opposite to |
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.3.7.
Air quality monitoring will be commenced depending on
the commencement of work for Contract no. HK/2009/02 under FEP-01/364/2009. The proposed
division of air monitoring stations are summarized in Table 5.9 below.
Table 5.9
Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society
for the Prevention of Cruelty to Animals |
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (
5.3.8.
Air quality monitoring will be
commenced depending on the commencement of work for Contract no. HY/2009/15
under FEP-06/364/2009/A. The
proposed division of air monitoring stations are summarized in Table 5.10 below.
Table
5.10 Air Monitoring Station for Contract
no. HY/2009/15
Station |
Description |
CMA3a |
CWB site
office at Wanchai Waterfront Promenade |
Contract no. HY/2009/17 –Central - Wan Chai
Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.4.1.
Inert C&D
waste was recycled in the reporting month. Details of the waste flow table are
summarized in Table 5.11
Table 5.11 Details
of Waste Disposal for Contract no. HY/2009/17
Waste Type |
Quantity
this month, m3 |
Cumulative
Quantity-to-Date, m3 |
Disposal
/ Dumping Grounds |
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert
C&D materials recycled |
317.80 |
1354.82 |
N/A |
Non-inert
C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
N/A |
N/A |
N/A |
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street under FEP-04/364/2009/A
5.4.2.
Inert C&D waste
was disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.12.
Table 5.12 Details
of Waste Disposal for Contract no. 04/HY/2006
Inert
C&D materials disposed |
NIL |
1288.5 |
Chai Wan and T.K.O. 137 |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
NIL |
NIL |
N/A |
Contract nos.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
5.4.3.
No inert and
non-inert C&D waste was disposed of in this reporting month. Details of the
waste flow table are summarized in Table 5.13.
Table
5.13 Details of Waste Disposal for Contract no. HK/2009/01
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
NIL |
NIL |
N/A |
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
5.4.4.
No inert and
no-inert C&D waste was disposed of in this reporting month. Details of the
waste flow table are summarized in Table 5.14.
Table
5.14 Details of Waste Disposal for Contract no.
HK/2009/02
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
NIL |
NIL |
N/A |
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
5.4.5.
No inert and
no-inert C&D waste was disposed of in this reporting month. Details of the
waste flow table are summarized in Table 5.15.
Table 5.15 Details
of Waste Disposal for Contract no. HY/2009/18
Inert
C&D materials disposed |
0 |
0 |
N/A |
Inert
C&D materials recycled |
0 |
0 |
N/A |
Non-inert
C&D materials disposed |
37.3 |
37.3 |
SENT Landfill |
Non-inert
C&D materials recycled |
0 |
0 |
N/A |
Chemical
waste disposed |
0 |
0 |
N/A |
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
5.4.6.
No inert and
no-inert C&D waste was disposed of in this reporting month. Details of the
waste flow table are summarized in Table 5.16.
Table 5.16 Details
of Waste Disposal for Contract no. HY/2009/15
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
NIL |
NIL |
N/A |
6.0.1.
The Event Action
Plan for construction noise, air qualities are presented in Appendix 6.1.
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
6.1.1.
No exceednace was recorded in the reporting month.
Contract
no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
6.1.2.
No exceedance
was recorded in the reporting month.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
6.1.3.
No noise monitoring was undertaken in the reporting month.
Contract
nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
6.1.4.
No noise monitoring was undertaken in the reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
6.1.5.
No noise monitoring was undertaken in the reporting month.
Contract no. HY/2009/17 – Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
6.2.1.
No exceednace was recorded in the reporting month.
Contract
no. HY/2009/17 – Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
6.3.1.
No exceedance was recorded in the reporting month.
Contract
no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
6.3.2.
No exceedance
was recorded in the reporting month.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
6.3.3.
No air quality monitoring was undertaken in the reporting month.
Contract
nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
6.3.4.
No air quality monitoring was undertaken in the reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
6.3.5.
No air quality monitoring was undertaken in the reporting month.
6.3.1.
There was no
non-compliance from the site audits in the reporting period. The observations
and recommendations made in each individual site audit session were presented
in Section 8.
6.3.2.
No
project-related non-compliance from monitoring was recorded in the reporting
month.
6.4.1.
There was no
particular action taken since no project-related non-compliance was recorded
from the site audits and environmental monitoring in the reporting period.
7.0.1.
According to
Condition 3.4 of the EP-364/2009/A, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WDII), Central-WanChai Bypass (CWB) and Island Eastern
Corridor Link projects (IECL).
7.0.2.
From the Monthly
EM&A report (December 2010) of Central Reclamation Phase III the key works
in January 2011 are as follows:
·
Architectural
works and commissioning tests at Pier 7;
·
Wet
Trades and Architectural works at the Lower, middle and upper decks of Pier 8
and steel frame for roof glazing;
·
CTB
installation of clock into the clock tower, architectural and E & M works
& link bridge construction;
·
Piling
(Socket H-Pile & Rock Anchors) and tie beam works at Public Pier West;
·
Testing
and Commissioning of Pump Station P5.1;
·
Electricity
Cable laying to Piers and to ESBs S11.1 & S11.2 (temporary);
·
MYS
Footbridge – cross head construction and steel frame fabrication (off Site);
·
MYS
storm drainage, sewers, watermains and roadworks to pier areas;
·
MYS
Laying of 800 dia. Cooling
·
MYS
Existing Culvert F – preparation for desilting and stabilisation works for
culvert.
·
MYS
Culvert F Extension –preparation for piling for Bay 1;
·
General
filing works above +2.5mpd in IRAE;
·
In
situ work to caisson and pumping stations’ seawall copings;
·
Internal
E&M works to IRAE pump stations;
·
ESB
(S8.1 & S9.1) –Installation of generators and cabling works;
·
ESB
(S11.1 & S11.2) –ABWF and E&M works;
·
Culvert
J piling and structural works;
·
Bored
piling at Eastern Seawall and;
·
Cooling
water main construction in
7.0.3.
According to the
construction programme of Wan Chai Development Phase II, Central-Wan Chai
Bypass and Island Eastern Corridor Link projects, the major construction
activity under Wan Chai Development Phase II was the filling works at North
Point Reclamation Stage 1(NPR1), dredging works at Wan Chai Reclamation Stage
1(WCR1), Advanced piling
works at FEHD Whitfield Depot and cross-harbour water mains in the reporting month. The major
environmental impact was water quality impact at North Point and Wan Chai. Land-based
construction activity was only the modification works of bus terminus near
7.0.4.
The major environmental
impacts generated from the Central Reclamation Phase III were located along the
coastline of Central and Admiralty while modification works of bus terminus
near
.
8.0.1.
During this
reporting month, weekly environmental site audits were conducted for Contracts
no. HY/2009/17 and 04/HY/2006. No non-conformance was identified during the
site audits.
8.0.2.
Five site inspections for Contract no. HY/2009/17 were
carried out during this reporting period. The results of these inspections and
outcomes are summarized in Table 8.1.
Table
8.1 Summary
of Environmental Inspections for
Contract no. HY/2009/17
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
101228_01 |
28-Dec-10 |
The
contractor was reminded to use more sedimentation tanks for treating silty
water at the exit of construction site. As one tank is not enough withstand
the high flow rate |
Increase the
number of sedimentation tank |
Completion
as observed on 4-1-11 |
101228_02 |
28/12/2010 |
Drip tray
shall be provide for chemical storage, if it is not practicable, place
tarpaulin under the chemical and surrounded by sand bags |
Provide drip
tray for chemical storage |
Completion
as observed on 4-1-11 |
101228_03 |
28-Dec-10 |
Cement bags over 20 packs shall be covered |
Cover
Cement by fabric fiber |
Completion
as observed on 4-1-11 |
110104_01 |
04-Jan-11 |
The
contractor is reminded to enhance the enclosure of the sieve grouting plant
after finishing the material transport |
Enhance the
enclosure of grouting plant |
Completion
as observed on 12-1-11 |
110112_01 |
12-Jan-11 |
The
contractor is reminded implementing of wheel washing facilities as
soon as practicable.
As mud was found at the exit of the construction site |
Increase
the rate of wheel washing facilities construction |
Completion
as observed on 18-1-11 |
110125_01 |
25-Jan-11 |
To
prevent silty water overflow North Point Reclamation drainage outfall. The contractor
is reminded to use an idle sedimentation tank near the using one. |
Increase the
number of use of sedimentation tank |
Completion
as observed on 1-2-11 |
8.0.3.
Five site inspections for Contract no. 04/HY/2006 were carried out during
this reporting period. The results of
these inspections and outcomes are summarized in Table 8.2.
Table 8.2 Summary
of Environmental Inspections for Contract no. 04/HY/2006
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
101230_01 |
30-Dec-10 |
Drip tray
shall be provide and gather the chemical storage |
provide
drip tray for gathering and storage chemical |
Completion
as observed on 03-Jan-11 |
9.0.1.
No complaint, notification of summons and prosecution was received in
the reporting month. The details of cumulative complaint log and updated summary of complaints are presented in Appendix
9.1.
9.0.2.
Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting
Period |
No. of
Complaints |
January 2011 |
0 |
Project-to-Date |
0 |
Table 9.2 Cumulative Statistics on Successful Prosecutions
Environmental
Parameters |
Cumulative
No. Brought Forward |
No. of
Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2. The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table
10.1 Summary of Key Construction
Activities of Individual Contract(s) to be commenced in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation
Measures |
HY/2009/17 |
·
Drilling,
installation steel H-Pile & grouting |
·
Noise barrier shall be implemented; ·
Watering any dust
generating activities; and Improvement of wheel washing facilities Improvement and increasing the number of sedimentation tanks. ·
|
04/HY/2006 |
·
N/A |
·
N/A |